Alto's Signal Bridges

Author: David Larrabee

On Saturday the 16th NS set up 4 cranes and in the space of less than an hour removed 4 signal bridges controled by Alto at Cove and Slope. The new signals for 'CP Altoona' now control movements at the west end of the complex. Here is a summary of the process very well carried out by a large crew. /DL